Analysis of executed contracts

Permenergo

Year Contracts executed, pcs Contracts executed, MW
2008 4 792 78.52
2009 5 780 144.26
2010 6 919 101.54

In 2010 6 919 contracts were executed (+19.7% on 2009, +44.4% on 2008) with overall capacity 101.5 MW (-29.6% and +29.3% correspondingly). Connected capacity volume in 2009 is higher, because in 2009 we executed a large-size individual contract with RZHD. In comparison to 2008, during the reported period there was a significant increase in connected applicants. This growth mainly was caused by increase of connections for applicants demanding capacity up to 15 kW.

Sverdlovenergo

Year Contracts executed, pcs Contracts executed, MW
2008 1 305 27.67
2009 1 974 30.34
2010 2 364 125.82

In 2010 2 364 contracts were executed (+19.7% on 2009, +81.1% on 2008) with overall capacity 125.82 MW (+314.7% and +354.6%). A considerable growth of connected capacity was caused by the execution of contracts with Terra Group, ОАО (10.1 MW), Urals Pig Complex, ZАО (3 MW and 1.6 MW), NPK Uralvagonzavod, ОАО (6 MW), Sukholozhsktsement, ОАО (34.85 MW), Kamensk-Uralski Metallurgy Plant, ОАО (12.5 MW), Rosenergoatom Beloyarskaya AES, ОАО (12 MW), Pervouralsk Novotrubnyi Zavod, ОАО (16 MW), Uralgidromed, ОАО (5 MW).

Chelyabenergo

Year Contracts executed, pcs Contracts executed, MW
2008 1 836 45.87
2009 1 742 37.63
2010 2 245 46.31

In 2010 2 245 contracts were executed (+28.9% on 2009, +22.3% on 2008) with overall capacity 46.31 MW (+23.1% and +1.0% correspondingly). Connected capacity slightly exceeded 2008 results. This shows that we return to pre-depression connection levels. At the same time the quantity of connected applicants grew significantly. This growth is due to the increase in connection of applicants with capacity up to 15 kW.